A Brief Concepts to Commissioning
Commissioning is the phase in a project when design process fluids are introduced to the process.
Note that for hydrocarbon systems the commissioning activities commence with inerting operations.
Commissioning activities normally consist of activities associated with running or operating the plant
and include operating adjustments necessary for satisfactory operation of the plant or part there of.
Also included are “Functional checks” which are methods used to prove that an item of mechanical
equipment or control system functions correctly.
Before completion of Pre-commissioning activities we can not move to commissioning phase .
Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Frequently,however, Pre-Commissioning activities overlap Mechanical Completion activities.
Pre-Commissioning activities include: checking for design conformity, checking the status of electrical, mechanical and instrument installations, running-in of equipment, flushing and cleaning activities, drying, etc.
Pre-Commissioning Period:
The site phase of the project will commence at approximately
60% construction completion and activities will
be mainly centred on:
Progression of all of the procedures developed during
the Home office phase of the project
Co-ordinating system turnover and completion
Monitoring and reporting progress
Co-ordinating resources, including sub-contract
and vendor support
Liaising with licensors.
Main activity developed during Pre-Commissioning
phase are:
Punch-Listing:
Punch-Listing will be undertaken on a systems basis. An
integrated team will be formed to participate in Punch Listing.
An initial Punch-List will be undertaken immediately
prior to system handover for Pre-Commissioning
purpose. This will probably occur at around the hydrotest
time. Punch-List items generated at this stage will be incorporated
into the Project master Punch-List system.
A final Punch-List will be undertaken by system immediately
prior to the commencement of commissioning
activities. This will be a less stringent Punch-List and
aimed at checking the system over before introducing
hydrocarbons. Utilisation of the Pre-Commissioning
check sheets will assist in completing a full range of required
checks. Punch-Listing progress will be recorded
on an A3 set of P&IDs.
System Cleaning :
This would include directing the cleaning of systems either
by flushing, blowing or chemical cleaning by issuing
directives for the necessary temporary connections,
utilities and proper line up of the system to be cleaned.
When the services of a chemical cleaning subcontractor
are required, the Commissioning Team will monitor
his performance to ensure a satisfactory cleaning job.
Before each system is closed for operating, the lines
and equipment would be inspected for cleanliness.
Cleaning progress will be recorded on an A3 set of
P&IDs.
Equipment Run-In:
This would include planning and co-ordinating Vendor
representatives for the running in of the equipment and
obtaining the necessary utilities to accomplish the runin
for equipment such as blowers, pumps, compressor,
motors, turbines, and other machinery or mechanical
equipment without process fluids before start-up.
Vessel Loading:
This phase would ensure that all catalysts, packing,
resins and desiccant loading is performed in a proper
manner and accurate records and samples of each
material loaded are retained.
" When all the activities foreseen in the Pre-Commissioning
phase (the Process Units will be ready to receive
hydrocarbons, most of the utility systems will be
live to the respective units and all of the hydrocarbon
lines will be positively isolated at the unit battery limits)
have been performed successfully a Ready for Commissioning
Certificate will be issued and so Commissioning
activities can start."
Commissioning & Start-Up Period:
Once the unit is precommissioned, the Commissioning
Team will conduct the following main activities:
- Purging
- Leak Test / Tightness Test
- Function Test
The Commissioning Subcontractor Team would take
care in troubleshooting any operating or process problems,
should they arise, and would investigate any operating
deviations as they occur.
Team will:
a.) Develop and Review Specific Operating Instruction
b.) Conduct and supervise all activities during the
Introduction of Feedstock to the Units
c.) Stabilize the Unit
Commissioning Complete :
When all commissioning for a process unit is completed
the unit is declared “Ready to Start-up”. At this
point normal conditions are established to produce the
designed products.
(fig.1)
(fig.2)
Above figures show the flowchart of pre-commissioning , commissioning activities which are to executed step by step for uninterupted performance guuarantee run test (PGTR) which is final phase/ step of commissioning of project.
No comments:
Post a Comment